Well Status – May 12

Installing PVC pipe at borehole at drilling site

May 12

Once we get the PVC pipe installed and pump test completed, we will have the information needed to know the real water outcome. We still need a water quality test before we can move ahead.

Our team in Tloma says:

We are now fitting PVC casing. Drilling ended at 210m though backfilling took about 6m so well depth is 204m due to the mud falling back in. Water level is at 158m meaning we have 46m of water [flowing underground between 158m and 204m depth]. After fitting the PVC pipe, we shall flash the well again and measure the water level.